Shumen Water Pumping Station Off-Grid Project, Bulgaria

  • Location: Shumen, Bulgaria
  • Configuration: PCS + 6 × E-MATE 125-261-L
  • Capacity: 1,566kWh
  • Application: PV+Storage
  • Year: 2026

Project Overview

Situated in the middle of farmland in Shumen, Bulgaria, this irrigation station operates in pure off-grid mode with no access to the power grid. It previously relied on diesel generators that ran around the clock, incurring millions in fuel and maintenance costs — a burden compounded when diesel prices nearly doubled within a few months.

In 2026, EENOVANCE delivered a 1,566 kWh PV-storage microgrid at the site, integrating six E-MATE 125-261-L battery cabinets (261 kWh each) with the plant's pre-installed PV array and Huawei 2 × 100 kW on-grid inverters. The cabinets operate in parallel under a master-slave configuration, powering irrigation pumps rated up to 90 kW.

EENOVANCE's BESS solution was adopted as a strategic approach to cutting operating costs while minimizing the facility's carbon footprint.

Challenges

Zero-Grid Fallback: The site operates completely isolated from the utility grid, leaving zero safety net for power deficits during extended periods of low renewable generation.

High Inrush Current & Black-Start Demand: Heavy motor loads (water pumps) generate massive inductive surge spikes, risking inverter over-current trips during start-up without grid inertia.

Severe Seasonal Solar Variance: Extreme drops in solar irradiance during spring and autumn demand a delicate balance between PV oversizing, battery bank autonomy, and operational cost.

Grid-Forming Frequency & Voltage Control: The system must act as a 100% grid-forming voltage source, maintaining phase balance and voltage stability under rapidly dynamic, unbalanced loads.

Solution

1. System Configuration

Component Details
PV Array Installed PV modules + Installed PV inverter
On-grid Inverter Installed Huawei, 2 × 100 kW
Liquid Cooling Battery Cabinet E-MATE 125-261-L × 6 · Total 1,566 kWh
Battery Parallel Junction Box EENOVANCE-Developed Core Component
  • The system adopts an off-grid topology.
  • The PV inverter and the energy storage system are both connected to the 400 V AC bus.
  • The EMS coordinates and schedules the entire system.
  • This configuration forms a stable PV-plus-storage microgrid.

2. Key Technical Innovations: PCS Update and Working in Grid-Forming

EENOVANCE R&D engineers specialize in Power Conversion System (PCS) upgrades, grid-forming control, and off-grid microgrid stabilization, with a proven track record in implementing Virtual Synchronous Generator (VSG) algorithms, parallel inverter synchronization, and seamless firmware updates for mission-critical energy storage systems. They are adept at transforming grid-following assets into stable, autonomous grid-forming voltage sources with full black-start capability.

Module Key Technical Points
1. PCS Maintenance & Upgrades Modular hot-swappable updates, Modbus/IEC 61850 protocol migration, firmware flashing, rollback protocols
2. Grid Forming Mode Virtual Synchronous Generator (VSG) logic, P/f and Q/V droop algorithms, synthetic inertia, dynamic frequency/voltage regulation
3. Microgrid Operations Multi-unit parallel load sharing, circulating current mitigation, black-start sequencing, transformer inrush management
4. Testing & Validation Hardware-in-the-Loop (HIL) simulation, DSP control loop tuning, system Factory Acceptance Testing (FAT)

Outcomes & Benefits

Post-expansion operation confirms all performance targets have been met, resolving long-standing power supply constraints at the water plant.

1. Cost Reduction

  • Predictable ROI: Fuel independence stabilizes long-term costs and hedges against energy market volatility.
  • Fast Payback: Fuel and maintenance savings typically recoup the investment within 3–5 years of continuous operation.
  • Automated Demand Management: Soft-start ramping powers heavy pumps cleanly, reducing mechanical wear and peak-power stress on motors.

2. Stability & Reliability

With six battery cabinets operating in parallel, the system delivers 20+ hours of continuous full-load backup. All pumps, filtration units, and control systems run uninterrupted, ensuring zero-downtime water supply, eliminating emergency-response costs, and protecting infrastructure from pressure surges.

3. Environmental and Social Value

  • Decarbonization: Replaces diesel with solar and LFP storage, cutting CO₂ and particulate emissions.
  • Soil & Water Protection: Eliminates fuel-leak and spill risks during transport, storage, and refueling.
  • Economic Stability: Stabilizes operating costs and shields communities from fuel-price spikes and rate hikes.
  • Local Capability Building: Trains local engineers on advanced grid-forming storage technology.

Diesel generator start-ups are down ~90%, saving several tons of CO₂ annually with far lower noise. Increased PV consumption strengthens the plant's ESG profile and supports green-subsidy and certification applications in Bulgaria.

Feedback from our client

"Transitioning our water infrastructure to this grid-forming solar and storage solution has completely transformed our operations. With six parallel E-MATE cabinets running seamlessly alongside the updated PCS, we survived a recent extended outage with zero pump downtime and over 20 hours of continuous full-load backup — without touching a drop of diesel. The elimination of generator noise and fuel logistics has been a massive win for our field team, and our operating costs have plummeted. It's rare to find an engineering solution that delivers this level of reliability, environmental value, and immediate ROI."

— the owner of Alfa Comers, Bulgaria